Features:  Task Update

Steelray provides an easy way for team members to send status updates to the project manager with just a few clicks.

The process is accomplished in 2 steps:

Step 1: The Project Manager Prepares the Project File

To prepare the project file for task updates with Steelray, the project manager sets the "Steelray Email" property in the project file:

Step 2: Send Task Updates From the Project Viewer

When Steelray opens a project file with the "Steelray Email" property set, it enables the Task Update feature. When the user clicks on a task name, the task detail view will have a third tab:  Update Task:


The first time you click on the tab, you'll be prompted to enter a little information about yourself and your email server:

After you answer a question about whether you've begun working on the task, you'll be asked more questions about the status. The questions change depending on how you answered the first question (whether the task has started).

Click the Update Task button, and Steelray sends an email to the project manager.